İş Programlarında Bolluk Yönetiminin Yüklenicilerin Süre Uzatim Taleplerindeki Önemi,örnek Çalışma

dc.contributor.advisor Dikbaş, Atilla tr_TR
dc.contributor.author Bayrak, Emre tr_TR
dc.contributor.department Proje Yapım Yönetimi tr_TR
dc.contributor.department Construction Management en_US
dc.date 2010 tr_TR
dc.date.accessioned 2010-07-06 tr_TR
dc.date.accessioned 2015-08-12T13:53:39Z
dc.date.available 2015-08-12T13:53:39Z
dc.date.issued 2010-07-13 tr_TR
dc.description Tez (Yüksek Lisans) -- İstanbul Teknik Üniversitesi, Fen Bilimleri Enstitüsü, 2010 tr_TR
dc.description Thesis (M.Sc.) -- İstanbul Technical University, Institute of Science and Technology, 2010 en_US
dc.description.abstract İnşaat projelerinde gecikmeler sıklıkla olagelmektedir, buna bağlı olarak yükleniciler kontratlarının gerekliliği olarak süre uzatım ve ilişkili maliyet taleplerini hazırlamaktadırlar. Bolluk dağıtımı ve doğru kullanımı yüklenicilerin süre uzatım talepleri içın çok önemli anahtar konuları oluşturmaktadir. Bu çalışma yüklenicilerin iş programlarındaki bolluk dağıtımlarının süre uzatım talepleri üzerindeki etkisini, bir yüksek bina projesi üzerindeki iki örnek çalışma ile tartışmaktadır. Birinci örnek çalışmada, yüklenicinin geçmiş bir yıllık dönemi içindeki gecikme ve hızlanma vakaları, pencere analiz tekniği kullanılarak, farklı risk kabullerinin yapıldığı sözleşme ve yüklenicinin dahili programında geçmişe dönük olarak analiz edilmiştir. Bu analizin sonucunda, programlarındaki aktivite süreleri gerek yüklenici tarafından saptırılmış, gerek risk faktörü eklenerek arttırılmış olsun, bu durumun yüklenicilerin süre uzatım taleplerinin tabiyatını değiştirdiği görülmüştür.Bu değişiklikler analizlerindeki gecikme hesaplamalarında azalmalara, geçmişde teslim edilmiş taleplerin geçerliliğını yitirmesine ve gelecekte yapılması planlanan haklı süre taleplerinin oluşamamasına sebebiyet verebilmektedir. İkinci örnek çalışmada ise örnek projenin şartları dikkate alınarak, yüklenicinin, kendi taşıdığı gecikme riskini nitelendirmek ve görselleştirmek amaçlı uygulanabilir bir model önerilmiştir. Bu modelin uygulanması ile iş programlarındaki bollukların proje yüklenicisi takımı tarafından daha iyi yönetebilinmesi ve iş programına dagıtılmasi amaçlanmaktadır. Bununla birlikte yanlış yönetilen bolluk sonucuna bağlı olarak, süre uzatım taleplerinin geçerliliğını yitirmesi de engellenebilir. Önerilen model sadece örnek proje için geliştirilmis olsada, ileride daha karmasik yapıya sahip projelerde kullanılmak üzere geliştirilebilir. tr_TR
dc.description.abstract Delays on construction project are common occurrences and, related to that contractors submit their extension of time and entitled damages as requirements of their contracts. The float allocation and its accurate usage are key points for success of contractors’ extension of time claims. This study discusses the importance of float allocation on contractor’s extension of time claims in two case studies on a high rise building project. On first case study, a forensic analysis has been introduced to demonstrate the delay events and accelerations on contractors’ contract and internal programme those represent different risk assumptions by using time impact analysis method. Analysis results indicate that no matter activity durations are increased by risk allocations or manipulation of contractor, float allocation and contingencies at activity durations may change the nature of contractors’ extension of time claims. Such changes may result in changes in the quantification of delay analysis, may affect the validity of previous extension of time claims and may eliminate the right of valid extension of time claims in future. The second part of study, a methodology is proposed to qualitative contractors own risks assumptions considering and analyzing the circumstances of case project. By the application of proposed methodology, the improvements, on management of float allocation and its reflection to progammes have been targeted. Additionally the impact of mismanaged float to the validity of extension of time claims can be minimized. Although the model has been developed for one case project, later improvements can be applied for adaptation of model on more complex projects. en_US
dc.description.degree Yüksek Lisans tr_TR
dc.description.degree M.Sc. en_US
dc.identifier.uri http://hdl.handle.net/11527/8337
dc.publisher Fen Bilimleri Enstitüsü tr_TR
dc.publisher Institute of Science and Technology en_US
dc.rights İTÜ tezleri telif hakkı ile korunmaktadır. Bunlar, bu kaynak üzerinden herhangi bir amaçla görüntülenebilir, ancak yazılı izin alınmadan herhangi bir biçimde yeniden oluşturulması veya dağıtılması yasaklanmıştır. tr_TR
dc.rights İTÜ theses are protected by copyright. They may be viewed from this source for any purpose, but reproduction or distribution in any format is prohibited without written permission. en_US
dc.subject Bolluk tr_TR
dc.subject iş programı tr_TR
dc.subject süre uzatımı talebi tr_TR
dc.subject hızlandırma tr_TR
dc.subject bolluk dağılımı tr_TR
dc.subject Float en_US
dc.subject acceleration en_US
dc.subject work programme en_US
dc.subject extension of time en_US
dc.subject float allocation en_US
dc.title İş Programlarında Bolluk Yönetiminin Yüklenicilerin Süre Uzatim Taleplerindeki Önemi,örnek Çalışma tr_TR
dc.title.alternative Importance Of Float Management In Contractor’s Extension Of Time Claims, A Case Study en_US
dc.type Master Thesis en_US
Dosyalar
Orijinal seri
Şimdi gösteriliyor 1 - 1 / 1
thumbnail.default.alt
Ad:
10752.pdf
Boyut:
2.94 MB
Format:
Adobe Portable Document Format
Açıklama
Lisanslı seri
Şimdi gösteriliyor 1 - 1 / 1
thumbnail.default.placeholder
Ad:
license.txt
Boyut:
3.14 KB
Format:
Plain Text
Açıklama